Location (province): Hubei Province |
Location (city): Wuhan |
Drilling rig type: MXL-150D2 |
Drill pipe configuration: 89 drill pipe |
Construction technology: drill pipe construction |
Stratigraphic condition: Sandy mudstone, strong weathering, gravel, groundwater |
Construction angle (degree): 30 |
Diameter (mm): 200 |
Depth(m): 18 |
Efficiency (H): 0.75 |
Net drilling time (H): 0.5 |
Net disassembly tool time (H): 0.25 |
Technology : |
1. Drilling tools: 8pcs of 89mm drill rods, two spiral drill pipes, turbodrill, equipped with 18m3/ 1.7 MPa air compressor. |
2.Requirements: anchor cable grouting 1. 30ºangle 2. hole diameter is 200mm 3. hole depth is 18m |
Process: |
1. Connect two spiral drill tods at first, and then connect turbine bit (spiral drill pipe is convenient for slag discharge. |
2. match holes. |
3. open gas, screw drill drilling, moving back and forth to slag. It is about 3 to 4 minutes. |
4. off gas, connect 2 meter long、 89mm drill rod , gas drilling,speed is about 1 minutes and 15 seconds. |
5. slagging, the power head moves back and forth with intermittent pause. The time is about 1 minutes and 15 seconds. |
6.connect 8pcs of 89mm drill pipes, drilling and slag discharge till work finished |
7. Remove the drill pipe, place the bottom thread-tooth between the upper and bottom clamp, tight the clamp, and loosen the thread-tooth. loose the clamp, lift up about 50 cm, tight the clamp, and unscrew the wire teeth. electric fork to clamp down the interface, reverse the upper tooth interface. |
8. Finish removing the drill pipe. Machine move to other place, put anchor cable in the pipe |